In the evening, W.M. Schultz will be working and pressure testing the waterline, continuing drainage installations and form and pour new sections of the bridge railing.
Utility work was scheduled to occur during the day beginning on Monday, July 9, at 7 a.m. with FairPoint digging test holes in the road by the Baptist Church. On Wednesday, July 11, at 10 a.m. a Belgium draft horse will be pulling the replacement cables for customers along Depot Street in the area of Thai Basil and the Town Green. On Friday night beginning at 9 p.m. July 13 CVPS plans to switch the power to the new lines from Hand Motors and Northshire Bookstore to the Riverside Condominiums. Completion is expected by 2 a.m. on July 14.