The following schedule of work on the roundabout is TENTATIVE and SUBJECT TO CHANGE

MANCHESTER - Night work this week will focus on replacing the water line from the Rite Aid to the Baptist Church. Drainage works gets underway at the Kimball property and work continues on building the forms for the bridge.

The latter involves a poured-in-place concrete railing.

Finish on the bridge railing will include a decorative wrought iron detail. Tuesday brings the paving of the Morrow driveway which will allow traffic to flow easily through the Hand/Bookstore properties.

Backlotting of the utilities continues. As of press time, FairPoint Communications will be digging test holes on Monday, July 9 by the Baptist Church in anticipation of the renovation of the pedestrian crossing to ADA handicapped standards.